Puerto Rico's Supreme Court cancels Luma Energy's power grid contract
Puerto Rico's Supreme Court ruled 5-4 on Wednesday to cancel the contract of Luma Energy, the private company that has run the island's power grid since 2021, though The Rio Times reports only the 2022 extension was voided and the original transition terms remain. The ruling gives Gov. Jenniffer González Colón's government a year to find a replacement operator.
Get The Augerton Digest by email.
The court found that a supplemental agreement between the government and Luma was never approved by the board of Puerto Rico's Public-Private Partnerships Authority, which oversees private operators, Bloomberg reported. Gov. Jenniffer González Colón said transmission and distribution will not revert to the Puerto Rico Electric Power Authority. She blamed Luma for "constant interruptions" and "unnecessary outages." The federal control board overseeing the island's finances said its immediate concern is keeping power service continuous. The ruling leaves open who will take over while outages persist.
Was this story useful?
What was the main problem? (optional)
Reporting behind this story
- Bloomberg — Puerto Rico Court Quashes Grid Contract in Win For Governor
- National Public Radio — Court lets Puerto Rico governor fire firm that runs the island's troubled power grid
- NBC News — Puerto Rico’s Supreme Court cancels power company contract as many wonder what’s next
- Al Jazeera — Puerto Rico’s Supreme Court cancels major power contract
- Bloomberg Law — Puerto Rico Court Quashes Grid Contract in Win For Governor
- Hartford Courant — Puerto Rico's Supreme Court cancels a key power contract. What's next?
- WRAL News — Puerto Rico Supreme Court cancels key power contract as many wonder what's next :: WRAL.com
- WSB-TV Channel 2 Atlanta — Top Puerto Rico court cancels key power contract as many wonder what's next - WSB-TV Channel 2
- Newser — Ruling Entangles Outlook for Puerto Rico's Power Supply
- The Rio Times — Puerto Rico Court Voids Power Grid Extension
- political.org — Puerto Rico Supreme Court Voids LUMA Energy Contract in 5-4 Ruling, Giving Governor a Year to Find New Grid Operator